Guides / Hacking walls: HDB rules before you plan

Can I hack this wall? HDB renovation rules to know before you plan your BTO layout

Updated 2026-11-22

An open kitchen, a bigger living room, two bedrooms joined into one: most layout ideas start with "can we hack this wall?" In an HDB flat the answer depends on the wall, and some work needs a permit from HDB before it starts. Here's what HDB's own guidance says, and how to plan your layout so the conversation with your contractor is quick and clear.

What needs an HDB permit

According to HDB's renovation guide on MyNiceHome, you need a permit from HDB before you:

You, the owner, are responsible for getting the permits before work starts. You can let your contractor apply online for you, and HDB asks that the contractor is listed in its Directory of Renovation Contractors. After approval, renovation in a new flat should be done within 3 months.

Walls you can't touch

HDB also has an e-service factsheet that lists renovation restrictions for your own BTO project and block. It's worth reading before you finalise a design, because some blocks have their own rules.

The 3-year rule for new bathrooms

For a newly built flat, HDB doesn't allow removing the wall or floor finishes in the bathrooms and toilets for 3 years. This protects the waterproofing under the tiles. If you don't like the tiles, you can lay new tiles over the existing ones instead of hacking them. After 3 years, changing the finishes or extending a bathroom needs an HDB permit. A glass shower screen doesn't need approval, but the floor slab must not be damaged when it's fixed.

This is also why the drainage test and bathroom check at key collection matter so much: once new tiles go on top, a slope or leak problem is much harder to prove and fix.

Noise hours

Hacking walls and removing floor or wall finishes counts as noisy work: Monday to Friday, 9am to 5pm only, and never on weekends, public holidays or the eve of major public holidays. Other works such as plastering run Monday to Saturday, 9am to 6pm. Plan your timeline around this, especially if you're moving in soon.

Plan the layout before you meet contractors

  1. Do your defect check first. Report defects to your Building Service Centre within one month of key collection and before renovation starts, so nobody can say your contractor caused them. Use the room-by-room checklist or the printable PDF.
  2. Try the layout on your plan. Our free 3D planner reads your HDB floor plan on your phone and turns it into a 3D model. You can take down or move walls, move doors and add furniture to see whether the open kitchen really feels bigger before anyone touches a hammer.
  3. Mark the walls you want changed and bring the picture to your contractor. Ask them directly: "Is this wall RC? Does this need a permit?" A good contractor answers before quoting.
  4. Check the permit is approved before hacking starts. HDB's "Check Renovation Permit" e-service shows the permit details.
  5. Check the work at the end with the renovation handover checklist before the final payment.

Rules can change, so treat this as a starting point. HDB's renovation guidelines on the HDB website and MyNiceHome are the final word, and your contractor's permit application is where your specific walls get checked.